#1
|
|||
|
|||
Resource not being marked as overallocated
Hi,
I'm having a problem where a resource is not being marked as over allocated despite being allocated to two tasks at the same day and time at 100% units. I've checked and there is no duplicate resource on the resource sheet, and the max units is 100%. Any ideas what I've done wrong? Thanks |
#2
|
|||
|
|||
Ok so I solved this one myself after much googling I found the level hour by hour option
|
#3
|
|||
|
|||
Thanks for posting your solution. I understand from your other post that you are working with clinical trials which are likely very time boxed. Usually, I would question whether you really have hour by hour control over your resources - my guess in that in your scenario you do.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Resource Usage View - Is it possible to display resource names | Andrea Schanz | Project | 6 | 09-22-2014 07:47 AM |
How to rotate (in Word2007) marked text by 90deg? | pstein | Word | 1 | 03-24-2012 04:31 AM |
overallocated column | ketanco | Project | 3 | 12-26-2011 09:26 AM |
Problem - Outlooked marked all emails as read | packman | Outlook | 1 | 11-17-2011 11:18 AM |
spacing marked the areas in red for all to see | bobafet | Word | 0 | 07-08-2010 12:40 PM |