I'm very new to project and have what I hope is not too annoyingly basic of a question!



I need to schedule multiple tasks, and link them in a way that they can occur in any order, but not simultaneously. Is there an easy way to do this? The only option I could think of was to add a resource and assign it to this task 100% but I thought that might go wrong down the road as I added other resources to the task.

The project I'm building it to manage a clinical trials team, so the reason the tasks cannot be simultaneous is that the trial participant obviously needs to be at them all.

Any help would be greatly appreciated!
Reply With Quote
  #2  
Old 06-08-2015, 09:02 AM
JulieS JulieS is offline Task link help Windows 7 64bit Task link help Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm afraid it's not possible.

By definition, when linking you are setting an order based upon the predecessor's start or finish and the successor's start or finish. Link them how you *think* it will happen and then be prepared to adjust when the trials start.

I imagine some sort of decision about which trials starts when is made before the trials actually start?
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
How to make a task adjust its end date depending on another task? (Newbie) ravl13 Project 3 07-27-2014 06:10 PM
Task link help Copy and Paste of a Task...Including all of the Task's 'children'...to a new task KRTSTARRYNIGHT Project 1 07-01-2014 06:54 AM
Task link help Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
how to make the task starts next day if no time enough today(task can not be split) duraid Project 1 10-25-2010 08:31 AM
Task link help Task link to email? markg2 Outlook 2 06-17-2010 10:20 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:43 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft