#1
|
|||
|
|||
Task link help
I'm very new to project and have what I hope is not too annoyingly basic of a question!
I need to schedule multiple tasks, and link them in a way that they can occur in any order, but not simultaneously. Is there an easy way to do this? The only option I could think of was to add a resource and assign it to this task 100% but I thought that might go wrong down the road as I added other resources to the task. The project I'm building it to manage a clinical trials team, so the reason the tasks cannot be simultaneous is that the trial participant obviously needs to be at them all. Any help would be greatly appreciated! |
#2
|
|||
|
|||
I'm afraid it's not possible.
By definition, when linking you are setting an order based upon the predecessor's start or finish and the successor's start or finish. Link them how you *think* it will happen and then be prepared to adjust when the trials start. I imagine some sort of decision about which trials starts when is made before the trials actually start? |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
How to make a task adjust its end date depending on another task? (Newbie) | ravl13 | Project | 3 | 07-27-2014 06:10 PM |
Copy and Paste of a Task...Including all of the Task's 'children'...to a new task | KRTSTARRYNIGHT | Project | 1 | 07-01-2014 06:54 AM |
Mid-Task resource scheduled 0 hours increasing task duration needlessly | DarlaWeber | Project | 1 | 01-31-2014 02:30 PM |
how to make the task starts next day if no time enough today(task can not be split) | duraid | Project | 1 | 10-25-2010 08:31 AM |
Task link to email? | markg2 | Outlook | 2 | 06-17-2010 10:20 AM |