#1
|
|||
|
|||
Percent Complete doesn't change End Date??
Why doesn't "% Complete" change the "Finish Date" for a Task. And how can I do that?
For example: Task A Work=20 hours Resource=John Start Date = Today End Date Calculated to be 12/14/09 Now say tomorrow I check with John, and he is way ahead of schedule; 50% Complete (10 hours left). So I update the % Complete=50 for Task A, but, the End Date stays the same! Obviously, what I want to do is have the end date move up - to refect that we are ahead of schedule (and John will finish early, thus starting his next task sooner. How can I do this in MS Project? Thanks very much! |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Word cannot complete the save due to a permissions error. | mpursel | Word | 2 | 12-05-2009 10:13 PM |
In Outlook 2003 auto complete won't work | Meenie | Outlook | 2 | 06-11-2009 08:24 AM |
Automatic Date Change | Marusja | Word | 0 | 03-04-2009 03:45 AM |
new appointment date always reverts back to today's date | msills | Outlook | 0 | 08-24-2007 08:57 AM |
Imported message date change to today's date | promark | Outlook | 1 | 12-23-2005 07:21 AM |