Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 12-07-2009, 07:59 PM
jrwpmw jrwpmw is offline Percent Complete doesn't change End Date?? Windows XP Percent Complete doesn't change End Date?? Office 2003
Novice
Percent Complete doesn't change End Date??
 
Join Date: Dec 2009
Posts: 1
jrwpmw is on a distinguished road
Default Percent Complete doesn't change End Date??

Why doesn't "% Complete" change the "Finish Date" for a Task. And how can I do that?

For example:
Task A Work=20 hours Resource=John
Start Date = Today
End Date Calculated to be 12/14/09

Now say tomorrow I check with John, and he is way ahead of schedule; 50% Complete (10 hours left). So I update the % Complete=50 for
Task A, but, the End Date stays the same!

Obviously, what I want to do is have the end date move up - to refect that we are ahead of schedule (and John will finish early, thus starting his next task sooner. How can I do this in MS Project?



Thanks very much!
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Word cannot complete the save due to a permissions error. mpursel Word 2 12-05-2009 10:13 PM
Percent Complete doesn't change End Date?? In Outlook 2003 auto complete won't work Meenie Outlook 2 06-11-2009 08:24 AM
Automatic Date Change Marusja Word 0 03-04-2009 03:45 AM
new appointment date always reverts back to today's date msills Outlook 0 08-24-2007 08:57 AM
Percent Complete doesn't change End Date?? Imported message date change to today's date promark Outlook 1 12-23-2005 07:21 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:00 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft