#1
|
|||
|
|||
Want to total duration and date to 1st floor
New to the site and MS project
I am trying to tie my location on the first floor to a total duration. I want to be able to change a start date and have all of the locations change dates All Plumbing Rough in on 1st floor - All HVAC Rough in on 1st Floor - I have 3 locations on the first floor – Lobby Registration – Entry Vestibule – Concierge Etc Per total location area (see Example) can this be done in MS Project Task Name Duration Start Finish Predecessors Interior Finishes First Floor South - TOTAL 203 days Wed 12/31/14 Fri 10/16/15 Location Totals 3 Plumbing rough in 9 days Mon 6/8/15 Thu 6/18/15 47 Run gas piping 3 days Mon 6/8/15 Wed 6/10/15 47 HVAC rough in 9 days Mon 6/8/15 Thu 6/18/15 47 Task Name Duration Start Finish Predecessors Lobby - Registration Plumbing rough in 3 days Mon 6/8/15 Thu 6/10/15 47 Run gas piping 1 days Mon 6/8/15 Wed 6/8/15 47 HVAC rough in 9 days Mon 6/8/15 Thu 6/10/15 47 Task Name Duration Start Finish Predecessors Entry Vestibule Plumbing rough in 3 days Mon 6/11/15 Thu 6/14/15 47 Run gas piping 1 days Mon 6/9/15 Wed 6/9/15 47 HVAC rough in 9 days Mon 6/11/15 Thu 6/14/15 47 Task Name Duration Start Finish Predecessors Concierges Plumbing rough in 3 days Mon 6/15/15 Thu 6/18/15 47 Run gas piping 1 days Mon 6/10/15 Wed 6/10/15 47 HVAC rough in 9 days Mon 6/15/15 Thu 6/18/15 47 |
#2
|
|||
|
|||
I'm sorry your post is exceptionally hard to follow. It appears as through everything is linked to task 47. So yes, if the schedule for task 47 changes, all successors would change automatically (assuming you have not typed in dates and are using auto-scheduled tasks.)
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Inconsistent Duration column for the same date ranges | ravl13 | Project | 3 | 07-28-2014 05:16 PM |
Make tasks Duration automatically change with date changes | Jedra | Project | 3 | 05-15-2014 05:47 AM |
remaining duration vs finish date | ketanco | Project | 3 | 02-17-2012 02:24 PM |
total slack not changing when changing duration | ketanco | Project | 1 | 02-11-2012 07:23 AM |
updating status date and actual duration | ketanco | Project | 5 | 01-27-2012 07:32 AM |