Glewis Glewis is offline Want to total duration and date to 1st floor Windows Vista Want to total duration and date to 1st floor Office 2010 32bit
Novice
Want to total duration and date to 1st floor
 
Join Date: May 2015
Posts: 1
Glewis is on a distinguished road
Default Want to total duration and date to 1st floor

New to the site and MS project

I am trying to tie my location on the first floor to a total duration. I want to be able to change a start date and have all of the locations change dates

All Plumbing Rough in on 1st floor - All HVAC Rough in on 1st Floor - I have 3 locations on the first floor – Lobby Registration – Entry Vestibule – Concierge Etc
Per total location area (see Example) can this be done in MS Project



Task Name Duration Start Finish Predecessors
Interior Finishes First Floor South - TOTAL 203 days Wed 12/31/14 Fri 10/16/15

Location Totals 3

Plumbing rough in 9 days Mon 6/8/15 Thu 6/18/15 47
Run gas piping 3 days Mon 6/8/15 Wed 6/10/15 47
HVAC rough in 9 days Mon 6/8/15 Thu 6/18/15 47


Task Name Duration Start Finish Predecessors
Lobby - Registration
Plumbing rough in 3 days Mon 6/8/15 Thu 6/10/15 47
Run gas piping 1 days Mon 6/8/15 Wed 6/8/15 47
HVAC rough in 9 days Mon 6/8/15 Thu 6/10/15 47

Task Name Duration Start Finish Predecessors
Entry Vestibule
Plumbing rough in 3 days Mon 6/11/15 Thu 6/14/15 47
Run gas piping 1 days Mon 6/9/15 Wed 6/9/15 47
HVAC rough in 9 days Mon 6/11/15 Thu 6/14/15 47

Task Name Duration Start Finish Predecessors
Concierges
Plumbing rough in 3 days Mon 6/15/15 Thu 6/18/15 47
Run gas piping 1 days Mon 6/10/15 Wed 6/10/15 47
HVAC rough in 9 days Mon 6/15/15 Thu 6/18/15 47
Reply With Quote
  #2  
Old 05-10-2015, 02:51 PM
JulieS JulieS is offline Want to total duration and date to 1st floor Windows 7 64bit Want to total duration and date to 1st floor Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm sorry your post is exceptionally hard to follow. It appears as through everything is linked to task 47. So yes, if the schedule for task 47 changes, all successors would change automatically (assuming you have not typed in dates and are using auto-scheduled tasks.)
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Want to total duration and date to 1st floor Inconsistent Duration column for the same date ranges ravl13 Project 3 07-28-2014 05:16 PM
Want to total duration and date to 1st floor Make tasks Duration automatically change with date changes Jedra Project 3 05-15-2014 05:47 AM
remaining duration vs finish date ketanco Project 3 02-17-2012 02:24 PM
Want to total duration and date to 1st floor total slack not changing when changing duration ketanco Project 1 02-11-2012 07:23 AM
updating status date and actual duration ketanco Project 5 01-27-2012 07:32 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:11 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft