Hi,
I have the following situation:
Task - 3days - 04/05/2015 - 06/05/2015

When I change the duration from 3 to 2 days, obviously the length of the bar chart reduces accordingly.
When I change the "Hours per day" from 8 to 12 in the File > Options> Schedule, Project recalculate the duration from 3 to 2days but the length of the bar chart remains unchanged, still stretching over 3 days instead of 2.

Can anyone explain to me why it is like that?
Thank you.
Reply With Quote
  #2  
Old 05-04-2015, 02:02 PM
JulieS JulieS is offline Bar chart Windows 7 64bit Bar chart Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

A change in the definition of "day" is only part of the process. You still need to change the number of working hours per day in Change Working Time.
Reply With Quote
  #3  
Old 05-06-2015, 12:48 PM
fridos fridos is offline Bar chart Windows 7 32bit Bar chart Office 2007
Novice
Bar chart
 
Join Date: May 2011
Posts: 10
fridos is on a distinguished road
Default Bar chart

Thanks Julie
Reply With Quote
  #4  
Old 05-07-2015, 07:17 AM
JulieS JulieS is offline Bar chart Windows 7 64bit Bar chart Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Chart with several factors iK2 PowerPoint 0 02-05-2015 01:33 AM
Bar chart MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table billcary Project 3 09-22-2014 07:10 AM
Bar chart Chart Mac235 Project 1 08-16-2013 05:52 AM
Chart Help DanZ Excel 0 10-12-2011 09:04 AM
Converting manual chart to bar chart? aligahk06 Excel 0 07-03-2010 12:23 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:55 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft