Bar chart
Hi,
I have the following situation: Task - 3days - 04/05/2015 - 06/05/2015 When I change the duration from 3 to 2 days, obviously the length of the bar chart reduces accordingly. When I change the "Hours per day" from 8 to 12 in the File > Options> Schedule, Project recalculate the duration from 3 to 2days but the length of the bar chart remains unchanged, still stretching over 3 days instead of 2. Can anyone explain to me why it is like that? Thank you. |
#2
|
|||
|
|||
A change in the definition of "day" is only part of the process. You still need to change the number of working hours per day in Change Working Time.
|
#3
|
|||
|
|||
Bar chart
Thanks Julie
|
#4
|
|||
|
|||
You're welcome.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Chart with several factors | iK2 | PowerPoint | 0 | 02-05-2015 01:33 AM |
MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table | billcary | Project | 3 | 09-22-2014 07:10 AM |
Chart | Mac235 | Project | 1 | 08-16-2013 05:52 AM |
Chart Help | DanZ | Excel | 0 | 10-12-2011 09:04 AM |
Converting manual chart to bar chart? | aligahk06 | Excel | 0 | 07-03-2010 12:23 PM |