JulieS JulieS is offline Durations are not correct Windows 7 64bit Durations are not correct Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You are correct. You can only set one defintion of "hours per day", "hours per week", and "days per month." So when you enter a task duration of 10 days, Project translates that to 80 working hours (assuming 8 hours per day). It will schedule the task based upon the working time in the calendar that is controlling that task.

The attached picture shows you the impact of the task calendar with a 12 hour per day, 6 days per week.

If you are going to have many circumstances where you are going to have different calendars (different hours per day) - you need to likely stop talking duration. Talk start dates, finish dates and work.
Attached Images
File Type: jpg tc.jpg (52.6 KB, 14 views)
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Durations are not correct Summarize durations by top level task tcdoha Project 1 01-10-2013 11:24 AM
Milestone durations fraserm Project 4 01-13-2012 08:43 AM
Adjusting All Durations by 10% skoz55 Project 1 01-13-2012 08:26 AM
Task and Summary Durations JR_12 Project 0 10-15-2011 05:07 PM
Calculate slide durations for song hb2010 PowerPoint 1 10-19-2010 06:41 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:52 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft