Old 04-25-2015, 07:30 PM
fridos fridos is offline Link tasks Windows 7 32bit Link tasks Office 2007
Novice
Link tasks
 
Join Date: May 2011
Posts: 10
fridos is on a distinguished road
Default Link tasks

Hi,
I have a group of tasks 11, 12,13 to link with another group of tasks 21, 22,23 as shown in the attached able.

The type of relationship between task11 and 21, between task12 and task22, and between task13 and task23 is the same (FS+7)


This is easy to do. However let's imagine having a group of 100 tasks (task1 to task100) followed by another group of 100 tasks (task101 to task200). Typing the same type of relationship in the predecessor column is tiring and time consuming. Is there anyway to automate this and save time please?
Thanks for assisting me
Attached Files
File Type: xlsx Table.xlsx (10.0 KB, 9 views)
Reply With Quote
  #2  
Old 04-29-2015, 08:42 AM
JulieS JulieS is offline Link tasks Windows 7 64bit Link tasks Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

No, I'm sorry I don't know of any automated way of doing this. You don't give much to go on, but can the tasks be arranged so the activities are grouped together? For example Task 21 is immediately below task 11?

It's tough to give advice without knowing what you are trying to accomplish.
Reply With Quote
  #3  
Old 05-01-2015, 02:37 AM
fridos fridos is offline Link tasks Windows 7 32bit Link tasks Office 2007
Novice
Link tasks
 
Join Date: May 2011
Posts: 10
fridos is on a distinguished road
Default

Hi Julie,
Thanks for the response.
Reply With Quote
  #4  
Old 05-04-2015, 02:03 PM
JulieS JulieS is offline Link tasks Windows 7 64bit Link tasks Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome and thanks for the feedback.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Link tasks OneNote Online "Sorry, OneNote Online can't open this link" (Link to a Page within a Section Group) ross5 OneNote 2 02-09-2015 06:16 PM
Trying to link page numbers in the footer, but refuses to link after new section fl0shizzle Word 7 05-06-2014 12:15 PM
updating not completed tasks or 0% tasks ketanco Project 3 08-24-2012 05:59 AM
How to link an object to a URL link to update automatically expert4knowledge Excel 1 06-11-2012 09:30 AM
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:14 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft