patrickd123 patrickd123 is offline Modifying default Gantt chart View Windows XP Modifying default Gantt chart View Office 2003
Novice
Modifying default Gantt chart View
 
Join Date: Dec 2011
Posts: 21
patrickd123 is on a distinguished road
Default Modifying default Gantt chart View

In my day to day, we work under a monthly release schedule. So, each month, a certain number of tasks are declared as completed. But I don't want to delete them in my MSP plan because of historical performance tracking.



So I created a column "Status" with an possible values of blank and "Archived". Therefore, each month, instead of deleting the completed tasks, I set their "Status" to "Archived".

I also created a filter to exclude the tasks set to Archived and went into the view organizer to add this filter to the Default Gantt chart view.

Problem: the Gantt chart view auto retores itself to the original setting without my filter. I seem to not be able to have the filter attached to it permanently.

Any solution?

Thanks
Reply With Quote
  #2  
Old 04-24-2015, 01:38 PM
JulieS JulieS is offline Modifying default Gantt chart View Windows 7 64bit Modifying default Gantt chart View Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

There's a couple of things going on. When you go to the organizer, you are simply making that filter available in all files you open on your machine.

If you want to create a view for "Archived" I suggest creating a new view and applying the filter to that view explicitly. Then you simply apply that view or apply the Gantt chart view or perhaps an "Active Projects" view.

Are you using Project 2003? If so, this is going to be from memory - so I may miss a few pieces:
  • Right click on the far left side (where it currently shows the active view name).
  • Choose More Views from the shortcut menu to open the More Views dialog.
  • Select the Gantt chart view and click Copy to open the View Definition dialog.
  • In the View Definition dialog, give the view a new name - perhaps Archived Projects" and select the custom filter you created. (I'm assuming your filter filters only for field = Archived.)
You may also find the built-in Completed Tasks filter works well if you are marking the tasks as complete.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Modifying default Gantt chart View Removing the Gantt chart from a view raminraiszadeh Project 3 02-13-2015 01:24 PM
Modifying default Gantt chart View Gantt calendar view deanop2 Project 3 09-04-2014 05:19 PM
Excel Gantt Chart Help kpk250 Excel 0 03-08-2013 08:46 AM
Bar in the Gantt chart with the duration ms_user Project 3 01-11-2013 06:31 AM
Modifying default Gantt chart View Gantt Chart with split view Intruder Project 5 12-20-2012 08:35 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:55 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft