Lightbulb Reds, but there still availability????


Ok, I'm putting this here for posterity as I looked for answers, could't find any and finally found the answer by myself after much sweat!!!!

Let's say you are in the resource usage view and you are zoomed to quarterly. Then, for some quarters, you see red numbers but, curiously, on that quarter you do have some availability !?!?!?!

The answer is that RED does not mean that you ran out of availibility for the period you are zoomed to, BUT it means that there is a day somewhere in your period where you are overallocated. So you have to drilldown by zooming in to spot the culprit day !

CQFD
Reply With Quote
  #2  
Old 06-17-2014, 02:47 PM
JulieS JulieS is offline Reds, but there still availability???? Windows 7 64bit Reds, but there still availability???? Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The overallocation flags in 2003 are controlled by the leveling settings. If you change the leveling to minute by minute you'll see red in many places you didn't see before. (I personally think leveling on less than day by day is unrealistic and in some circumstances I use week by week.)
Reply With Quote
  #3  
Old 04-24-2015, 10:09 AM
patrickd123 patrickd123 is offline Reds, but there still availability???? Windows XP Reds, but there still availability???? Office 2003
Novice
Reds, but there still availability????
 
Join Date: Dec 2011
Posts: 21
patrickd123 is on a distinguished road
Default

Indeed, the default seems to be day by day.

I changed it to week by week, which works best for me!

Flagging as solved
Reply With Quote
  #4  
Old 04-24-2015, 01:30 PM
JulieS JulieS is offline Reds, but there still availability???? Windows 7 64bit Reds, but there still availability???? Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Yes, the default in Project is always Day by Day. The good news is that if you change the leveling to Week by Week it "sticks" for all projects opened in that instance of Project. If however, someone else opens the project file and their settings are day by day you'll likely have some explaining to do.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Retrieve amount of calendar availability and attachments automatically imayachita Outlook 0 11-18-2013 08:26 PM
Visualisation of resource availability Antares Project 1 08-22-2011 02:36 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:39 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft