Showing how much work is required to complete a project according to summary task start/end times
I have a large schedule that has multiple deadlines for summary tasks.
I want to find out how the minimum amount of people I have to hire for a job to complete it in the timeframe. In other words I want Project to auto-calculate the Max % per Resource. Is Project 2013 capable of doing this? |
#2
|
|||
|
|||
No, sorry. You can set the tasks as Fixed Duration - assign the work and Project will calculate assignment units needed to complete the work within the duration - but it will not calculate max. units.
You should not assign resources to summary tasks. |
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
physical complete %, regular work, vs % complete | ketanco | Project | 1 | 06-16-2014 11:08 AM |
Rollup Summary Tasks to Project Summary Task | shep555 | Project | 1 | 05-24-2014 12:28 PM |
Team Planner-maintaining accuracy in task start and finish times | david_23 | Project | 9 | 04-19-2012 08:33 AM |
summary task calculating from project start | ketanco | Project | 1 | 01-02-2012 02:34 PM |
Different % complete in Project Center & View a Project | mikaelbelchior | Project | 1 | 01-25-2006 12:56 AM |