PDX-ADM-TRM01 PDX-ADM-TRM01 is offline Showing how much work is required to complete a project according to summary task start/end times Windows 7 64bit Showing how much work is required to complete a project according to summary task start/end times Office 2013
Novice
Showing how much work is required to complete a project according to summary task start/end times
 
Join Date: Dec 2014
Posts: 3
PDX-ADM-TRM01 is on a distinguished road
Default Showing how much work is required to complete a project according to summary task start/end times

I have a large schedule that has multiple deadlines for summary tasks.

I want to find out how the minimum amount of people I have to hire for a job to complete it in the timeframe. In other words I want Project to auto-calculate the Max % per Resource.



Is Project 2013 capable of doing this?
Reply With Quote
  #2  
Old 03-30-2015, 04:05 PM
JulieS JulieS is offline Showing how much work is required to complete a project according to summary task start/end times Windows 7 64bit Showing how much work is required to complete a project according to summary task start/end times Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

No, sorry. You can set the tasks as Fixed Duration - assign the work and Project will calculate assignment units needed to complete the work within the duration - but it will not calculate max. units.

You should not assign resources to summary tasks.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Showing how much work is required to complete a project according to summary task start/end times physical complete %, regular work, vs % complete ketanco Project 1 06-16-2014 11:08 AM
Rollup Summary Tasks to Project Summary Task shep555 Project 1 05-24-2014 12:28 PM
Showing how much work is required to complete a project according to summary task start/end times Team Planner-maintaining accuracy in task start and finish times david_23 Project 9 04-19-2012 08:33 AM
Showing how much work is required to complete a project according to summary task start/end times summary task calculating from project start ketanco Project 1 01-02-2012 02:34 PM
Different % complete in Project Center & View a Project mikaelbelchior Project 1 01-25-2006 12:56 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:03 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft