Hello,



I am managing a project that requires various tasks be performed by my staff at different sites (e.g. at our home lab, at a contract lab, and at a university). Is there a way to assign a physical location to the tasks?

Ideally, I'd like to be able to identify specific tasks and the respective locations at which the tasks will be performed on my calendar view (i.e. different bar colors represent different physical locations).

Any suggestions? Thank you!
Reply With Quote
  #2  
Old 04-04-2015, 06:44 AM
JulieS JulieS is offline Assigning tasks to be done at a physical location Windows 7 64bit Assigning tasks to be done at a physical location Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You have a couple of options:
  1. Include the location site in the name of the task.
  2. Use a spare text field (perhaps with a a lookup list) to select a location for the task. I'd set the default to your home lab if that is where the majority of the work is done.
As you your question about the Calendar view - the color choices for task bars are very limited in the Calendar view. You can use the marked field to change the color of bars in the Calendar view or apply a highlight filter. But if you have more than two locations this won't suit your needs. You can filter by Resource, or by location (using the spare text field), or by Resource and Location. Apply the filter in the Gantt chart view and then switch to the Calendar view to see the filtered tasks.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Physical % Complete and Task Duration ChuckM Project 3 02-09-2014 09:21 AM
Assigning tasks to be done at a physical location project for projected vs physical theWizardAKQ Project 3 01-24-2014 06:16 AM
Assigning tasks to be done at a physical location Assigning Resources to Tasks rickw262 Project 1 01-18-2013 04:46 AM
Outlook 2007 win7x32 Archive location/backup location question michael.monaco Outlook 0 11-19-2012 02:07 PM
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:21 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft