Is there any way to deactivate the warning that comes up when you schedule a task to start on a specific date rather than by setting a duration/predecessor? i.e. "Entering a start date is not the best way to schedule a task..."



I find the green flag in the cell distracting and as I'm scheduling milestones for key events that have no predecessor, I'm constantly having to address the warning by telling MSP to keep the task constrained to start on a specific day.
Reply With Quote
  #2  
Old 03-19-2015, 01:02 PM
JulieS JulieS is offline Turn off scheduling warning Windows 7 64bit Turn off scheduling warning Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Consider setting the tasks to manually scheduled and then you can type the dates to your heart's content.

If you want to use constrained, auto scheduled tasks and enter dates:
  1. File > Options.
  2. Display category.
  3. uncheck the option "Edits to start and finish dates" in the section "Show Indicators and Option Buttons for:".
Reply With Quote
  #3  
Old 03-20-2015, 05:59 AM
jjmclell jjmclell is offline Turn off scheduling warning Windows 7 32bit Turn off scheduling warning Office 2010 32bit
Advanced Beginner
Turn off scheduling warning
 
Join Date: Nov 2012
Location: Sault Ste. Marie, Canada
Posts: 52
jjmclell is on a distinguished road
Default

Many thanks...exactly what I was looking for.

Quote:
Originally Posted by JulieS View Post

If you want to use constrained, auto scheduled tasks and enter dates:
  1. File > Options.
  2. Display category.
  3. uncheck the option "Edits to start and finish dates" in the section "Show Indicators and Option Buttons for:".
Reply With Quote
  #4  
Old 03-20-2015, 07:28 AM
JulieS JulieS is offline Turn off scheduling warning Windows 7 64bit Turn off scheduling warning Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome and thanks for the feedback.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Turn off scheduling warning First To Finish Task Scheduling Jody Project 6 09-23-2011 07:06 AM
Scheduling of Tasks asmith1977 Project 0 01-27-2011 11:13 AM
Scheduling of presentations browe PowerPoint 0 12-14-2010 06:02 PM
Meeting scheduling - what rooms are available jgerrish Outlook 0 02-12-2010 02:35 PM
Turn off scheduling warning DRoster Employee Scheduling minime Excel 1 03-03-2009 08:09 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:16 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft