brymey brymey is offline Showing Actuals on a Completed Task Windows 7 64bit Showing Actuals on a Completed Task Office 2013
Novice
Showing Actuals on a Completed Task
 
Join Date: Feb 2015
Posts: 1
brymey is on a distinguished road
Default Showing Actuals on a Completed Task

Background: I have a team that is working on being better at estimating work for projects. We are a leveraged tem, so I seperate status using both work (8 hours) and Duration (6 days).


Problem: Right now I need to show our Estimated work (original hours) vs What we actually worked for that task (actual work), simple enough except, I am trying to do this while have the task completed = 100%. SO example would be task 1 Work (estimated) = 8 hours, actual hours = 6, with task 1 being complete (100%). I need the % to be updated for over all project status. our Project is 25% done and we are currently +/- hours to date from what we estimated. How do I do that?
Reply With Quote
  #2  
Old 02-27-2015, 04:21 AM
JulieS JulieS is offline Showing Actuals on a Completed Task Windows 7 64bit Showing Actuals on a Completed Task Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Your estimated work and duration is available in the Baseline Work and Baseline duration field - assuming you have saved a baseline.

Project will calculate variance for the baseline data as compared to actuals.

Regarding updating for the entire project, turn on the Project Summary task (Gantt Chart Format Ribbon). It will show overall project data including % complete.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Showing Actuals on a Completed Task Copy and Paste of a Task...Including all of the Task's 'children'...to a new task KRTSTARRYNIGHT Project 1 07-01-2014 06:54 AM
Strange behaviour when entering Actuals joday48 Project 4 01-15-2013 03:51 AM
Showing Actuals on a Completed Task several task must be completed out of hours, not split proj Project 1 01-13-2012 08:38 AM
the best way to enter actuals ketanco Project 3 12-26-2011 09:36 AM
Showing Actuals on a Completed Task actuals vs estimates projectman Project 23 11-15-2010 07:23 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:30 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft