Is there anyway in which the following is possible in MS Project 2013 without creating two resource profiles for one project resource?
Jon Doe works on a project Monday through to Friday. For the first three days on the week, Jon has a cost of £123.00 per hour (8 hours per day). For the 4th and 5th working day of the week, Jon has a zero cost (non-billable). I have tried to input multiple rates but cannot them to accumulate as I would like to do (see above). The other consideration is that if Jon only works between 1 and 3 days then these should all have a cost of £123.00 per hour. Anything over the 3 days should be zero costs. I cannot think of any other ways in which this could be done as well. Any suggestions would be gratefully appreciated. Regards Andy Last edited by OSandy; 02-24-2015 at 09:25 AM. Reason: Additional info provided |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
Mareike_# | Project | 5 | 12-01-2014 07:18 AM |
![]() |
Andrea Schanz | Project | 6 | 09-22-2014 07:47 AM |
Issue regarding calculating costs of rental equipment | TheCarrotcake | Project | 3 | 06-08-2014 02:14 PM |
![]() |
Trigger | Project | 1 | 04-26-2012 03:41 PM |
![]() |
ketanco | Project | 1 | 12-24-2011 12:56 PM |