#1
|
|||
|
|||
Interim Baselines
Hello
we have tried to set the Start and Finish into Start1 and Finish1 using the Project set interim baseline function. But this does not appear to be working, what is happening is that the Start is being copied into Finish 1? Can you please advise what might be happening here, we are using MS Project 2013 |
#2
|
|||
|
|||
This is a known issue with MSP 2013 and is scheduled to be fixed in the next SP.
See link: http://www.postseek.com/meta/269c991...e86c2a6d5cc198 Tony |
#3
|
|||
|
|||
I believe it was fixed in the Oct 2013 Cumulative Update.
See: https://support.microsoft.com/kb/2825651 I tested with Project 2013 updated through the last (Dec 2014) cumulative update and no longer see the issue. |
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Finding Earned Values for Different Baselines in a single project | pratik6312 | Project | 1 | 08-22-2013 11:18 AM |
Meaning of current date vs status date when saving baselines | ketanco | Project | 1 | 02-08-2012 02:20 PM |
Help with Interim Baseline Variance | poyns | Project | 1 | 05-27-2010 10:59 AM |