Old 02-10-2015, 11:32 AM
jamiespear jamiespear is offline Tasks with higher priorities Windows 7 32bit Tasks with higher priorities Office 2013
Novice
Tasks with higher priorities
 
Join Date: Feb 2015
Posts: 1
jamiespear is on a distinguished road
Default Tasks with higher priorities

I am having trouble defining a task constraints.



I have multiple tasks for one individual to do that has multiple interruptions - see below:

Task 1 - Design widget, duration 1 week, completed by resource 1

Task 2 - Manufacture widget, duration 2 weeks, completed by resource 2, to follow task 1

Task 3 - Test widget, duration 1 week, completed by resource 1, to follow task 2

Task 4 - Redesign widget, duration 1 week, completed by resource 1, to follow task 3

Task 5 - Manufacture redesigned widget, duration 2 weeks, completed by resource 2, to follow task 4

Task 6 - Design crate, duration 12 weeks, completed by resource 1, to be worked on during down time when resource 2 is doing supporting work (task 3 and 5) - how do I make these constraints flow into one task to create an overall timeline?

Thanks,

Jamie
Reply With Quote
  #2  
Old 02-10-2015, 03:29 PM
JulieS JulieS is offline Tasks with higher priorities Windows 7 64bit Tasks with higher priorities Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I think your question has already been answered at:

https://social.technet.microsoft.com...nal2010general

But to clarify. You do not need to set constraints on the tasks. Set the "Build Crate" task to a lower priority number (200 for example) and ensure the option to Split tasks in Leveling options is selected.

I'm also guessing you wanted the Build Crate task to occur during Task 2 & 5.
Attached Images
File Type: jpg schedule.jpg (55.5 KB, 15 views)
Reply With Quote
Reply

Tags
interrupt, split

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Layout: Numbered long headings on level 10 or higher Katarina Word 3 05-07-2014 02:56 PM
Question about updating Microsoft Office 2007 to 2010 or any higher editions x4north Office 2 03-06-2014 09:13 AM
Tasks with higher priorities find and navigation dialogue in Word 2010 and higher franklekens Word 3 09-18-2013 10:24 AM
Top of 2nd page higher than 1st Anne at ppf Word 7 03-23-2013 07:55 AM
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:01 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft