Old 02-09-2015, 04:07 PM
raminraiszadeh raminraiszadeh is offline What are the implications of changing project start date Windows 7 64bit What are the implications of changing project start date Office 2013
Novice
What are the implications of changing project start date
 
Join Date: Sep 2014
Posts: 22
raminraiszadeh is on a distinguished road
Default What are the implications of changing project start date

My project start date is set to 09/2014. What happens if I change the project start date to 02/2015?



I have tasks that started in 09/2014. What will happen to these and other tasks?

Thank you
Reply With Quote
  #2  
Old 02-10-2015, 03:13 PM
JulieS JulieS is offline What are the implications of changing project start date Windows 7 64bit What are the implications of changing project start date Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

It depends upon whether you have updated the task from Sept 2014 or not. If your tasks are auto scheduled, constrained with no constraint other than ASAP, and do not have an actual start date, then changing the start date of the project should change the dates for all tasks.

If you have set Actual Start dates then you will get a message from Project about tasks before a Project start date when you try to move the start date.

Have you entered progress against any tasks? I'm guessing you have negotiated a new baseline?
Reply With Quote
  #3  
Old 02-11-2015, 02:42 PM
raminraiszadeh raminraiszadeh is offline What are the implications of changing project start date Windows 7 64bit What are the implications of changing project start date Office 2013
Novice
What are the implications of changing project start date
 
Join Date: Sep 2014
Posts: 22
raminraiszadeh is on a distinguished road
Default

Thanks very much Julie!

I spot-checked several tasks and their start/finish dates did not get affected by the project date changed (which is good).

At the time I changed the project start date, I had not created any baselines (which is also good).

A few of the tasks were 100% complete. These were also not impacted by the date change.

Question: Why did you ask about the baseline?

Thanks again!
Reply With Quote
  #4  
Old 02-11-2015, 03:13 PM
JulieS JulieS is offline What are the implications of changing project start date Windows 7 64bit What are the implications of changing project start date Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome and thanks for the feedback.

Once a task has an actual start date, it won't move nor will a task that is 100% complete.

I asked about the baseline because I wouldn't want to be compared against a baseline on a project that started 4 months late :-)
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Task with Start date but no Due date? bplat Outlook 0 01-12-2012 08:10 AM
What are the implications of changing project start date Groups to be sorted by start date in MS Project Antares Project 3 12-09-2011 03:17 PM
What are the implications of changing project start date MS Project Start Dates not matching the Status Date sjodom Project 3 12-04-2011 08:45 AM
What are the implications of changing project start date Project start date steve138 Project 4 05-20-2011 04:55 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:24 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft