Project 2013 - Change GANTT Bar Colour By Main Task Date
 
Join Date: Feb 2015
Posts: 1
CaelanT is on a distinguished road
Default Project 2013 - Change GANTT Bar Colour By Main Task Date

I want to change GANTT chart bar colours based on date to flag items which are late. Scenario as follows:

I have a main task which runs from February 1st through March 1st. I have several indented deliverables listed under this main task with various dates they need to be completed by, e.g. delivery of a specific component. This component is scheduled due on February 1st but supplier tells me it will be 5 days late. When I change the finish date to 5th February I want the bar to automatically turn red as a visual indicator.



Similarly, if the date for the main task slips by 7 days and becomes February 7th, when I change the date for this task I want any late tasks which would as a result now not be late to turn back to green.

Is there a way to do this? (Basically driving sub-task bar colour by the main tasks start and/or finish date.

Thanks in advance for any help with this.
Reply With Quote
  #2  
Old 02-09-2015, 12:50 PM
JulieS JulieS is offline Project 2013 - Change GANTT Bar Colour By Main Task Date Windows 7 64bit Project 2013 - Change GANTT Bar Colour By Main Task Date Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Posted and answered at:

https://social.technet.microsoft.com...ct2010custprog
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Project 2013 - Change GANTT Bar Colour By Main Task Date Newbie q - Create a filter for report in ms project 2013 task due in 2 weeks bypm Project 7 07-10-2015 06:19 AM
Project 2013 - Change GANTT Bar Colour By Main Task Date MS Project to detect task level changes and record a date modified in custom field RJTMEYER Project 3 08-22-2014 07:38 AM
Project 2013 - Change GANTT Bar Colour By Main Task Date checking tasks complete from main gantt view sundance1 Project 1 01-29-2013 10:31 AM
Project 2013 - Change GANTT Bar Colour By Main Task Date How to Change/Edit the Bottom Task Area in Office Project 2007? Rahmat_uk20 Project 3 06-07-2012 02:54 PM
Stop the % Complete of subatasks from counting against the Main task bzeyger Project 0 06-08-2010 06:19 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:41 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft