  #1  
Old 02-05-2015, 08:40 AM
sssb2000 sssb2000 is offline Question about leveling a project..... Windows XP Question about leveling a project..... Office 2007
Novice
Question about leveling a project.....
 
Join Date: Sep 2010
Posts: 6
sssb2000 is on a distinguished road
Question Question about leveling a project.....

Hi,


I think i understand the purpose of leveling in a project file....i'm currently setting up a level of effort estimate.
after finishing the schedule, i noticed that i have several tasks with overallocated resources....leveling all tasks should take care of this, i thought.

i clicked Level All (using MS Project 2013) and it took away all the resource conflicts, the total project dollar amount is the same, and the project is ending on the same date as before. great.....but then i noticed some of the tasks and their information being a bit odd:

for example, one of the tasks that was scheduled for 10 days, starting on 4/1 to 4/15 is now showing as 10 days, starting on 4/1 to 5/14, the cost of the task remaining the same.

can someone explain that for me please? why is it showing as 10 days, when the duration is clearly more? is it essentially saying that during the 4/1 to 5/14 time frame, 10 full days worth of work is being done?
Reply With Quote
  #2  
Old 02-05-2015, 10:40 AM
JulieS JulieS is offline Question about leveling a project..... Windows 7 64bit Question about leveling a project..... Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If you have allowed tasks to be split during leveling, Project will take a task and "chunk" it into smaller pieces. As long as the task is not Fixed Duration, the splits (where the task is not working) will not count in the duration.
Reply With Quote
  #3  
Old 02-05-2015, 11:23 AM
sssb2000 sssb2000 is offline Question about leveling a project..... Windows XP Question about leveling a project..... Office 2007
Novice
Question about leveling a project.....
 
Join Date: Sep 2010
Posts: 6
sssb2000 is on a distinguished road
Default

Quote:
Originally Posted by JulieS View Post
If you have allowed tasks to be split during leveling, Project will take a task and "chunk" it into smaller pieces. As long as the task is not Fixed Duration, the splits (where the task is not working) will not count in the duration.
understood.
thank you.
how does one allow or not allow a task to be split?
Reply With Quote
  #4  
Old 02-05-2015, 12:11 PM
JulieS JulieS is offline Question about leveling a project..... Windows 7 64bit Question about leveling a project..... Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If you don't want project to split any task, you can remove the check from "Leveling can create splits" in the Resource Leveling options. If you only want some tasks not be split, add the "Leveling can split" field to a task view and change it to "no" for tasks you do not want split.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Question about leveling a project..... VB Project in PowerPoint 2007/10 (Game Concept Question) theculpeppers PowerPoint 4 11-07-2014 06:08 AM
Question about leveling a project..... How do you shut off/ignore resource leveling pmgreen Project 1 08-22-2014 06:54 AM
Question about leveling a project..... MS Project 2010 - 'Who Does What When' report question jrdunn78hawk Project 5 06-24-2014 07:00 AM
Question about leveling a project..... resource leveling in ms project ketanco Project 1 12-24-2011 12:58 PM
Question about leveling a project..... New to project - Predecessor Question geissap Project 1 01-20-2011 10:00 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:30 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft