Hi,
I think i understand the purpose of leveling in a project file....i'm currently setting up a level of effort estimate. after finishing the schedule, i noticed that i have several tasks with overallocated resources....leveling all tasks should take care of this, i thought. i clicked Level All (using MS Project 2013) and it took away all the resource conflicts, the total project dollar amount is the same, and the project is ending on the same date as before. great.....but then i noticed some of the tasks and their information being a bit odd: for example, one of the tasks that was scheduled for 10 days, starting on 4/1 to 4/15 is now showing as 10 days, starting on 4/1 to 5/14, the cost of the task remaining the same. can someone explain that for me please? why is it showing as 10 days, when the duration is clearly more? is it essentially saying that during the 4/1 to 5/14 time frame, 10 full days worth of work is being done? |
#2
|
|||
|
|||
If you have allowed tasks to be split during leveling, Project will take a task and "chunk" it into smaller pieces. As long as the task is not Fixed Duration, the splits (where the task is not working) will not count in the duration.
|
#3
|
|||
|
|||
Quote:
thank you. how does one allow or not allow a task to be split? |
#4
|
|||
|
|||
If you don't want project to split any task, you can remove the check from "Leveling can create splits" in the Resource Leveling options. If you only want some tasks not be split, add the "Leveling can split" field to a task view and change it to "no" for tasks you do not want split.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
VB Project in PowerPoint 2007/10 (Game Concept Question) | theculpeppers | PowerPoint | 4 | 11-07-2014 06:08 AM |
How do you shut off/ignore resource leveling | pmgreen | Project | 1 | 08-22-2014 06:54 AM |
MS Project 2010 - 'Who Does What When' report question | jrdunn78hawk | Project | 5 | 06-24-2014 07:00 AM |
resource leveling in ms project | ketanco | Project | 1 | 12-24-2011 12:58 PM |
New to project - Predecessor Question | geissap | Project | 1 | 01-20-2011 10:00 AM |