Quote:
Originally Posted by JulieS View Post
You can assign resources at less than 100% to indicate that the resource doesn't generate the 10 hours of work per day - there are other things that take away from the "productive" time.
For example, you have a task that has a work budget of 50 hours - original duration 5 -10 hour days. But during a given week (5 days) the resource can only 8 hours of work per day. So in a duration of 50 hours, the resource can only generate 80% or 40 hours of work. If the task really is 50 hours of work, the duration will be 6.25 days.
Julie; Thanks for the response;
The scheduler developed the view below in P6. What are the tables in MS projects that reflect the Original Duration, Remaining Duration, Budgeted Labor Units and Remaining Labor Units and how can I create that view in MS? Also what is a quick way to assign all resources 80 % and which task type is needed to keep the duration hours the same when assigning less time to the resource? In other words the estimated time that has been provided for each activity was developed by the team with the acknowledgement that there is about 20% fat in the estimated duration. This duration was used as the basis of the estimate. In order to track actuals against cost, what is the best way to setup the resource allocation?



P6 view
Activity Name,Start, Finish, OD,RD, Budgeted Labor Units,Remaining Labor Units
Reply With Quote
  #17  
Old 01-01-2016, 10:36 AM
bnkglb bnkglb is offline [Project 2013] More accuracy with resource, unit %, and cost? Windows 10 [Project 2013] More accuracy with resource, unit %, and cost? Office 2016
Novice
 
Join Date: Dec 2015
Posts: 3
bnkglb is on a distinguished road
Default What is the Work table representing

The attachment shows a view from the LRI MS schedule I have been working on. I don't understand the Work table and what it is indicating. Can someone provide what the work table indicates?

https://www.msofficeforums.com/attac...1&d=1451669252


Quote:
Originally Posted by bnkglb View Post
Julie; Thanks for the response;
The scheduler developed the view below in P6. What are the tables in MS projects that reflect the Original Duration, Remaining Duration, Budgeted Labor Units and Remaining Labor Units and how can I create that view in MS? Also what is a quick way to assign all resources 80 % and which task type is needed to keep the duration hours the same when assigning less time to the resource? In other words the estimated time that has been provided for each activity was developed by the team with the acknowledgement that there is about 20% fat in the estimated duration. This duration was used as the basis of the estimate. In order to track actuals against cost, what is the best way to setup the resource allocation?

P6 view
Activity Name,Start, Finish, OD,RD, Budgeted Labor Units,Remaining Labor Units
Attached Images
File Type: png Snag it 2016-01-01_12-09-41.png (53.4 KB, 8 views)
Reply With Quote
  #18  
Old 01-02-2016, 01:50 PM
JulieS JulieS is offline [Project 2013] More accuracy with resource, unit %, and cost? Windows 7 64bit [Project 2013] More accuracy with resource, unit %, and cost? Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome.
To your questions:
What are the tables in MS projects that reflect the Original Duration, Remaining Duration, Budgeted Labor Units and Remaining Labor Units and how can I create that view in MS?

There is not a table in Project that captures all of that data. However, you can create your own custom table to reflect some (sadly not all) of the information you are looking for.
Original Duration = Baseline Duration
Remaining Duration = Remaining Duration
Budgeted Labor Units - sorry no corresponding field there is Baseline Work
Remaining Labor Units - Remaining Work

For step by step on creating the new table and view:
https://msdn.microsoft.com/en-us/lib...(v=vs.90).aspx

Also what is a quick way to assign all resources 80 % and which task type is needed to keep the duration hours the same when assigning less time to the resource?

If you create the resources with max units of 80%, that is what Project will assign by default. You can also select multiple tasks and assign multiple resources using the Assign Resources Dialog. If you want to make sure duration does not change if you change assignment units - first set the task as Fixed Duration.

In order to track actuals against cost, what is the best way to setup the resource allocation?

Create the resources with the appropriate standard cost. Project will calculate cost - save a baseline and track.
Reply With Quote
  #19  
Old 01-02-2016, 01:51 PM
JulieS JulieS is offline [Project 2013] More accuracy with resource, unit %, and cost? Windows 7 64bit [Project 2013] More accuracy with resource, unit %, and cost? Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hard to tell what is going on in the screen shot. My guess is that the resources are assigned to the tasks at a low assignment unit.
Take a look at the Task Usage view, add the Peak field. That should show you what is going on.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Remove resource name from Gannt Bar in Project Professional 2013? nick@johansens.eu Project 1 10-16-2014 05:58 AM
[Project 2013] More accuracy with resource, unit %, and cost? How to add A fixed cost per day for the duration of the project? vdLRSA Project 3 08-11-2014 02:26 PM
[Project 2013] More accuracy with resource, unit %, and cost? Need totoal cost despite project being in progress Sognamed Project 1 07-23-2013 06:06 AM
Portfolio Analyzer Cube - Cost Resource Question seanpears99 Project 2 03-07-2013 06:59 PM
entering values for a cost type resource ketanco Project 3 12-26-2011 09:25 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:08 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft