Hello,
How can i see the costs per task seperated into materials costs and work costs? Tnx |
#2
|
|||
|
|||
![]()
In the Task Usage view, add the Cost field.
Add the Text1 field and create a formula: [id] & " " & [Name] Create a custom group with the following definition: Group by: Field: Text1 Field Type: Task Order: Ascending Then By: Field: Resource Type Field Type: Assignment (you'll need to check off the option "Group assignments not tasks" Order: Ascending Apply the group. Does it get you what you need? |
![]() |