MS Project - Start/end and duration.
I am adding new task in plan.
task-1 thru 4. each with 50hrs The schedule options are set to I thought since we set the hours per day to 10, it should have scheduled each task to only 5 days.. first from 1/19 thru 1/23.. second 1/26 thru 1/30.. it's not working that way.. can someone guide? Thanks in advance. |
#2
|
|||
|
|||
In addition to changing the hours per day, you also need to change the working time in the project calendar. Project tab, Change working time. Then change your default state and default end time to match what you have set in the calendar.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Fixed end but variable start (and duration) | meileetan | Project | 3 | 08-22-2014 06:54 AM |
Project baseline duration | Alka | Project | 1 | 11-20-2012 05:09 AM |
start and finish dates exceeding duration | joday48 | Project | 0 | 06-27-2012 04:55 AM |
baseline duration, start and finsih dates | ketanco | Project | 1 | 04-09-2012 09:47 AM |
duration vs actual start and finish dates | ketanco | Project | 1 | 12-14-2011 09:06 AM |