I am adding new task in plan.
task-1 thru 4. each with 50hrs The schedule options are set to I thought since we set the hours per day to 10, it should have scheduled each task to only 5 days.. first from 1/19 thru 1/23.. second 1/26 thru 1/30.. it's not working that way.. can someone guide? Thanks in advance. |
|
![]() |
||||