Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 11-19-2014, 01:45 PM
MSPuser MSPuser is offline HUGE BUG? Baseline Dates And Duration Windows 7 32bit HUGE BUG? Baseline Dates And Duration Office 2010 32bit
Novice
HUGE BUG? Baseline Dates And Duration
 
Join Date: Nov 2014
Posts: 2
MSPuser is on a distinguished road
Default HUGE BUG? Baseline Dates And Duration

Can anyone tell me why you can type non-dates into baseline date fields and non-durations into baseline duration fields in MS Project 2010? I do a fair amount of programming to MS Project, and it should be known that when you delete a baseline date, it isn't really gone. In the backend, it stays to whatever "real" date it last had regardless if you remove it or overwrite it with a non-date value.

In MS Project 2007, it validated the date/duration and would not allow it. Not sure what 2013 does..

Really looking forward to responses on this one!



Thanks
Reply With Quote
  #2  
Old 11-20-2014, 04:57 AM
JulieS JulieS is offline HUGE BUG? Baseline Dates And Duration Windows 7 64bit HUGE BUG? Baseline Dates And Duration Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

With the introduction of Manually scheduled tasks the Baseline fields (as well as Start, Finish, Duration) will accept text entries. The Baseline estimated Finish field only accepts date/time data.

Not a bug - by design.
Reply With Quote
  #3  
Old 11-20-2014, 05:22 AM
MSPuser MSPuser is offline HUGE BUG? Baseline Dates And Duration Windows 7 32bit HUGE BUG? Baseline Dates And Duration Office 2010 32bit
Novice
HUGE BUG? Baseline Dates And Duration
 
Join Date: Nov 2014
Posts: 2
MSPuser is on a distinguished road
Default

Thanks for your post. I didn't notice the Baseline estimated dates until you mentioned it. Not a bug, but an interesting design. Looking at the documentation it says that for automatically scheduled tasks, the values in the Baseline Start fields and the Baseline Estimated Start fields are exactly the same; unfortunately they are not as you can still have text in one and not the other.

Oh well, moving on.
Reply With Quote
  #4  
Old 11-20-2014, 03:27 PM
JulieS JulieS is offline HUGE BUG? Baseline Dates And Duration Windows 7 64bit HUGE BUG? Baseline Dates And Duration Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If you save a baseline through the usual route, the "usual" Baseline fields will match the Estimated Baseline fields for auto scheduled tasks. You are correct, you can alter the data in the Baselines (including Estimated) as you always have been able to. I believe the baselines can be "locked" against alteration in the Project Server - not just client however.
Reply With Quote
Reply

Tags
baseline fields



Similar Threads
Thread Thread Starter Forum Replies Last Post
HUGE BUG? Baseline Dates And Duration Amending dates and recalculating duration seanpears99 Project 1 12-03-2012 07:18 AM
Project baseline duration Alka Project 1 11-20-2012 05:09 AM
HUGE BUG? Baseline Dates And Duration baseline duration, start and finsih dates ketanco Project 1 04-09-2012 09:47 AM
HUGE BUG? Baseline Dates And Duration baseline duration of summary not updating. why ketanco Project 1 12-14-2011 09:07 AM
HUGE BUG? Baseline Dates And Duration duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:18 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft