Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #2  
Old 11-20-2014, 04:57 AM
JulieS JulieS is offline HUGE BUG? Baseline Dates And Duration Windows 7 64bit HUGE BUG? Baseline Dates And Duration Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

With the introduction of Manually scheduled tasks the Baseline fields (as well as Start, Finish, Duration) will accept text entries. The Baseline estimated Finish field only accepts date/time data.

Not a bug - by design.
Reply With Quote
 

Tags
baseline fields



Similar Threads
Thread Thread Starter Forum Replies Last Post
HUGE BUG? Baseline Dates And Duration Amending dates and recalculating duration seanpears99 Project 1 12-03-2012 07:18 AM
Project baseline duration Alka Project 1 11-20-2012 05:09 AM
HUGE BUG? Baseline Dates And Duration baseline duration, start and finsih dates ketanco Project 1 04-09-2012 09:47 AM
HUGE BUG? Baseline Dates And Duration baseline duration of summary not updating. why ketanco Project 1 12-14-2011 09:07 AM
HUGE BUG? Baseline Dates And Duration duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:24 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft