inserting someone elses schedule dates for comparison
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default inserting someone elses schedule dates for comparison

I have my own schedule for a job but i need to show the differences between my schedule and another persons schedule (for the same job of course) on my own schedule.

which column should i use for entering his dates? it will not be one to one matched activities but i can still match many items or at least summary activities so that is no problem but i like to know which column should i use for entering and then for comparison too

for example to enter their start and finish dates should i use one of the start1,2,3,4.... and finish 1,2,3,4 columns?

and then how can i show the difference between my finish and start dates and his finish and start dates? i dont need to enter his links , just entering his dates are enough (i didn't see how i can enter his links anyway)
Reply With Quote
  #2  
Old 10-29-2014, 11:00 AM
JulieS JulieS is offline inserting someone elses schedule dates for comparison Windows 7 64bit inserting someone elses schedule dates for comparison Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You can use any of the spare date fields you like - Start1 etc or Date1. To show the difference use a spare Duration (Duration1) column to calculate the difference between the two dates. DateDiff or ProjDateDiff functions should work.
Reply With Quote
  #3  
Old 10-30-2014, 03:18 AM
Guloluseus Guloluseus is offline inserting someone elses schedule dates for comparison Windows 7 64bit inserting someone elses schedule dates for comparison Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

It may not be what you are looking for, but if you have the same tasks (as in same name) I woul duse th ecompariosn feature (Under Project/ Compare Reports). This will give you all dates for both programmes, as well as a visual indicator of where the differences are. I have found this useful, especially for larger projects, where a visual can save an awful lot of time.
Reply With Quote
  #4  
Old 10-30-2014, 06:05 AM
JulieS JulieS is offline inserting someone elses schedule dates for comparison Windows 7 64bit inserting someone elses schedule dates for comparison Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Quick note for clarification: the Compare Projects tool will only work on two copies of the same file. If the OP created a project and the other user created a separate project file, the Compare Projects tool won't work.
Reply With Quote
  #5  
Old 10-30-2014, 01:06 PM
ketanco ketanco is offline inserting someone elses schedule dates for comparison Windows 7 64bit inserting someone elses schedule dates for comparison Office 2010 64bit
Expert
inserting someone elses schedule dates for comparison
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

yes my project and his are totally different files with similar but different WBS. so i can use key and common activities from his schedule to compare my dates but not everything on our schedules is done the same way.
Reply With Quote
  #6  
Old 10-30-2014, 02:26 PM
JulieS JulieS is offline inserting someone elses schedule dates for comparison Windows 7 64bit inserting someone elses schedule dates for comparison Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Then you cannot use the compare project utility. You'll need to manually enter his dates into spare fields and perform the calculations in a duration field.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Slow "comparison/replace" script mavCZ Excel Programming 53 07-27-2014 10:57 AM
inserting someone elses schedule dates for comparison Changing Actual Finish dates changes original Finish dates SomewhereinTX Project 3 12-20-2013 10:25 AM
inserting someone elses schedule dates for comparison Complex date comparison/Selection using fields instead of VBA Fields Word 8 06-06-2012 05:13 PM
Saving & reopening comparison MarshallAbrams Word 0 03-29-2012 06:19 AM
Comparison jumps to end MarshallAbrams Word 2 03-21-2012 04:04 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:55 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft