#1
|
|||
|
|||
finish no later than constraint
my last activity on the project was finishing lets say on November 1. When I put a finish no later than constraint to the last activity as something before november 1, such as October 31, it reduces the toatl float by 1 day and makes the total float of critical path as -1, which i understand but when i put a finish no later than constraint to that activity as november 2, nothing changes. should this not increase the total float of critical path? |
#2
|
|||
|
|||
I'm guessing you mean the total slack returns to zero? FNLT constraints (as long as they are not violated) will not add positive total slack. You are merely saying the task needs to finish by a certain date - but it can finish earlier. If you wish to add total slack - set a must finish on.
|
Thread Tools | |
Display Modes | |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
flag to indicate finish date does not equal baseline finish date | TCB | Project | 3 | 08-06-2014 02:49 PM |
Start No Later Than constraint | EC37 | Project | 3 | 05-13-2014 10:13 AM |
Changing Actual Finish dates changes original Finish dates | SomewhereinTX | Project | 3 | 12-20-2013 10:25 AM |
activities getting constraint dates vs starting as soon as possible | ketanco | Project | 1 | 08-30-2012 05:27 AM |
Update Progress breaks with constraint | benwimpory | Project | 1 | 03-14-2012 08:44 AM |