finish no later than constraint
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default finish no later than constraint

my last activity on the project was finishing lets say on November 1. When I put a finish no later than constraint to the last activity as something before november 1, such as October 31, it reduces the toatl float by 1 day and makes the total float of critical path as -1, which i understand

but when i put a finish no later than constraint to that activity as november 2, nothing changes. should this not increase the total float of critical path?
Reply With Quote
  #2  
Old 10-25-2014, 04:30 PM
JulieS JulieS is offline finish no later than constraint Windows 7 64bit finish no later than constraint Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm guessing you mean the total slack returns to zero? FNLT constraints (as long as they are not violated) will not add positive total slack. You are merely saying the task needs to finish by a certain date - but it can finish earlier. If you wish to add total slack - set a must finish on.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
flag to indicate finish date does not equal baseline finish date TCB Project 3 08-06-2014 02:49 PM
finish no later than constraint Start No Later Than constraint EC37 Project 3 05-13-2014 10:13 AM
finish no later than constraint Changing Actual Finish dates changes original Finish dates SomewhereinTX Project 3 12-20-2013 10:25 AM
finish no later than constraint activities getting constraint dates vs starting as soon as possible ketanco Project 1 08-30-2012 05:27 AM
finish no later than constraint Update Progress breaks with constraint benwimpory Project 1 03-14-2012 08:44 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:55 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft