  #1  
Old 10-21-2014, 04:38 AM
Peasy Peasy is offline Programme not levelling - MSP 2013 Windows 7 64bit Programme not levelling - MSP 2013 Office 2013
Novice
Programme not levelling - MSP 2013
 
Join Date: Sep 2014
Posts: 16
Peasy is on a distinguished road
Default Programme not levelling - MSP 2013

Hi

I am putting together a "planned maintenance schedule" for some buildings that the company I work for manage.

I've set a years worth of recurring tasks of 30 minutes each, on a Friday for the fire panel tests, and a years worth of recurring tasks for 2.5h each on various dates of the month fro emergency light tests (ie, some buildings have theirs on the 4th of every month, some the 20th etc).

I've assigned "Dave" to all the resources. As one would imagine, the little red man appears in the indicators column quite a bit. When I hit "level all", nothing is moved. I have (I think) tried everything, and read as many help files as I can see, and nothing seems to work.



The only thing I can do link the tasks with Finish to Start links... ie so when Friday 20/3 fire panel test in building A is done, link it to building B on Friday 20/03, then building C, then D etc and then go back to building A for Friday 27/03. This is going to take me forever and surely levelling should work whether the tasks are linked or not?

Please can someone help!?
Reply With Quote
  #2  
Old 10-21-2014, 07:02 AM
JulieS JulieS is offline Programme not levelling - MSP 2013 Windows 7 64bit Programme not levelling - MSP 2013 Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

A couple of questions:

Are the tasks manually or auto scheduled?
Have you created the "fire test" task for multiple buildings or only one? How many buildings are involved - more than 16?

What are your leveling settings (day by day, week by week)?

Are you getting any messages back from Project when you attempt to level Dave?
Reply With Quote
  #3  
Old 10-21-2014, 09:02 AM
Peasy Peasy is offline Programme not levelling - MSP 2013 Windows 7 64bit Programme not levelling - MSP 2013 Office 2013
Novice
Programme not levelling - MSP 2013
 
Join Date: Sep 2014
Posts: 16
Peasy is on a distinguished road
Default

Quote:
Originally Posted by JulieS View Post
A couple of questions:

Are the tasks manually or auto scheduled?
Have you created the "fire test" task for multiple buildings or only one? How many buildings are involved - more than 16?

What are your leveling settings (day by day, week by week)?

Are you getting any messages back from Project when you attempt to level Dave?
Hi

Thanks for the reply

- They're all auto scheduled
- The fire test task is on 6 buildings, between 30 - 60 minutes each (4.5h in total and a 8 hour day), they're all scheduled at the beginning of the day.
- The levelling settings were by day, but I set it to minutes
- No messages regarding Dave, I click "Level all" and nothing happens, the little red man stays there and the bars on the chart don't move.


Its the same with the Emergency Light Test, 2.5 hours a day on 18 buildings. 6 of the buildings with a light test also have the fire test.
Reply With Quote
  #4  
Old 10-21-2014, 09:51 AM
JulieS JulieS is offline Programme not levelling - MSP 2013 Windows 7 64bit Programme not levelling - MSP 2013 Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'd first look at the Resource Usage view to see what is causing the overallocation. Clearly if Dave is only working 4.5 hours - he isn't overallocated on a day by day setting. Leveling from the Gantt view (where you see the little red men) is mostly useless - you have no idea why he's overallocated, no idea what tasks are causing the issue.
Reply With Quote
  #5  
Old 10-22-2014, 01:07 AM
Peasy Peasy is offline Programme not levelling - MSP 2013 Windows 7 64bit Programme not levelling - MSP 2013 Office 2013
Novice
Programme not levelling - MSP 2013
 
Join Date: Sep 2014
Posts: 16
Peasy is on a distinguished road
Default

Quote:
Originally Posted by JulieS View Post
I'd first look at the Resource Usage view to see what is causing the overallocation. Clearly if Dave is only working 4.5 hours - he isn't overallocated on a day by day setting. Leveling from the Gantt view (where you see the little red men) is mostly useless - you have no idea why he's overallocated, no idea what tasks are causing the issue.
Ah so am I supposed to level from the resource usage view? I will have a look and try it now

ETA - OK, I went on resource view and can see day by day that Dave is red. However, he is red, even when he is only doing 0.64 days. His calendar is the standard calendar. I cant think of anything else I need to check...
Reply With Quote
  #6  
Old 10-22-2014, 03:48 AM
Peasy Peasy is offline Programme not levelling - MSP 2013 Windows 7 64bit Programme not levelling - MSP 2013 Office 2013
Novice
Programme not levelling - MSP 2013
 
Join Date: Sep 2014
Posts: 16
Peasy is on a distinguished road
Default

OK, I think I have worked out what is wrong.

It doesn't seem to like recurring tasks.

I have put some more work in there for our painters. Painting only gets done once a year on the buildings, except for one, where its 2 days a month.

So for all the buildings needing painting, I put in the relevant duration for the year and for the odd building, a recurring tasks, once a month to the end of the year. When I levelled the 2 resources on painting, it moved everything either before or after the recurring task.

Im making the tasks just individual now, to see how they go.




If anyone else has any comments, I would appreciate it
Reply With Quote
  #7  
Old 10-22-2014, 04:47 AM
JulieS JulieS is offline Programme not levelling - MSP 2013 Windows 7 64bit Programme not levelling - MSP 2013 Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Recurring tasks are constrained with a Start No Earlier than constraint and also have a leveling priority of 1000 - meaning do not level. You may have more success changing the priority (add the field to the Gantt chart view) to something below 1000 - the lower the number, the more likely it is to be leveled.

You'll also want to allow tasks to be split so they will not be delayed until all of the recurring tasks are complete.

And do not use leveling hour by hour. That is what is causing the overallocations when your resource isn't working a full day. Leave it at Day by Day.
Reply With Quote
  #8  
Old 10-23-2014, 01:01 AM
Peasy Peasy is offline Programme not levelling - MSP 2013 Windows 7 64bit Programme not levelling - MSP 2013 Office 2013
Novice
Programme not levelling - MSP 2013
 
Join Date: Sep 2014
Posts: 16
Peasy is on a distinguished road
Default

Quote:
Originally Posted by JulieS View Post
Recurring tasks are constrained with a Start No Earlier than constraint and also have a leveling priority of 1000 - meaning do not level. You may have more success changing the priority (add the field to the Gantt chart view) to something below 1000 - the lower the number, the more likely it is to be leveled.

You'll also want to allow tasks to be split so they will not be delayed until all of the recurring tasks are complete.

And do not use leveling hour by hour. That is what is causing the overallocations when your resource isn't working a full day. Leave it at Day by Day.
Thanks I will try these today and let you know how I get on


ETA - JulieS - you are a gem, it works perfectly, thank you so much for your help
Reply With Quote
  #9  
Old 10-23-2014, 07:35 AM
JulieS JulieS is offline Programme not levelling - MSP 2013 Windows 7 64bit Programme not levelling - MSP 2013 Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Great, I'm glad you were able to get everything to work and thanks for the feedback.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Programme not levelling - MSP 2013 Levelling resource's units to calculate duration task codeghi Project 10 03-01-2014 08:13 AM
Programme not levelling - MSP 2013 MS Project - Maximizing resource levelling aguatorito Project 3 03-10-2013 06:08 AM
Priority based levelling for split tasks having actuals proj12 Project 3 02-27-2012 06:47 AM
Programme not levelling - MSP 2013 How to copy contact list to another programme ksimmonds Outlook 2 01-13-2011 06:46 AM
Programme not levelling - MSP 2013 Recurring tasks falling on weekends - programme for working day prior guyc Project 3 09-26-2010 03:32 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:22 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft