Stop column
what is stop column for exactly? i read the definition, which says it is the end of the actual portion of the task. but what does this mean? is there a non actual portion? if something is done, it is always actual. if something is not done, it is incomplete
|
#2
|
|||
|
|||
For tasks that are not complete, the Stop field is the "complete through" date. For example, I create a task beginning on October 20, 10 days duration with a finish date of Oct 31. I set a status date of yesterday Oct 22 at 5:00 pm and use the Update Project command to update the task as of the status date. The Stop date = status date - the complete through date. The actuals (actual work and actual duration) are marked the appropriate % complete and % work complete through Oct 22.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Parsing 'FullName' column - help needed text to column | ScottA | Excel Programming | 3 | 05-06-2014 12:49 PM |
Columns. How to move the left column so it's to the right of the 'right' column ? | Vit | Word | 9 | 11-21-2012 12:57 PM |
Automatically enter date into a column and make that column read only | Mr Davo | Excel | 1 | 10-29-2012 01:07 AM |
Can I change the horizontal scrollbar to scroll smoothly rather than column by column | carpat | Excel | 0 | 01-10-2012 09:34 AM |
Need to search a column for a macth and return a result from a third column | pdfaust | Excel | 2 | 02-03-2011 03:02 PM |