#1
|
|||
|
|||
Automatic calculation of summary tasks
Hi again, I'm facing the issue that for some reason summary tasks do not auto-calculate. I have a custom field that displays a duration, yet, when I enter durations to subtasks, the value in the summary task remains 0. Calculating after each edit is enabled. Any ideas? It worked before but stopped at some point. |
#2
|
|||
|
|||
Ok, found it myself. The custom field had the calculation set to "none" instead of Rollup:Sum
|
|