#1
|
|||
|
|||
![]()
is there a way to apply a calendar only to a range of activities? or i must select one by one?
|
#2
|
|||
|
|||
![]()
Select the tasks, click the Information button, click the Advanced tab, select the calendar.
|
![]() |
|
![]() |
||||