Should I start the post by: Julie? lolll
Hi, I have a feeling that this is not doable but will still ask: I have been given the 2015 project slate layed out per month workload. But the workload is non uniform. So is there a way to enter different work value for each month on a given task? |
#2
|
|||
|
|||
![]()
Hi Patrick,
Sorry for the delay. The work on a single task could vary if: Resources are not working the entire span of the task. For example Resource1 starts work on Day 1 but Resource 2 & 3 don't start until Day 8. You can certainly manually edit time-phased work in the Task Usage or Resource usage view. Julie |
![]() |