shane_dav71 shane_dav71 is offline Microsoft Project  Managing Planned / Earned Value & Actual Costs Windows 8 Microsoft Project  Managing Planned / Earned Value & Actual Costs Office 2013
Novice
Microsoft Project  Managing Planned / Earned Value & Actual Costs
 
Join Date: Oct 2014
Posts: 1
shane_dav71 is on a distinguished road
Default Microsoft Project Managing Planned / Earned Value & Actual Costs


Hi,

I am new to this forum and would consider myself an intermediate user of Microsoft project in the past for setting up project schedules etc.

I am have set-up a detailed project for a future project I am to manage. In this program there are approximately 800 line items; a tree structure has been set-up with parent / children / grand children tasks on many levels (the .mpp file has been attached to this forum as a .zip file for reference).

I want to further develop my skills to set-up within the program baseline costs for the project - where I allocate allowed costs from our budget to some of the parent / child / grand child tasks so that initially the overall budget is stored within the program and upon which planned spend over the duration of the project can be determined (by use of graphs / charts / summed values etc).

I then want to manage the costs as the project progresses, including earned value costs and actual costs against planned costs.

The trouble I am having as a newbie to this analysis is finding relevant "dumbed down" information on the internet to complete such activities. There is information out there, and Microsoft Project itself seems to be capable of an infinite number of reports if you know how to enter data etc. Even starting by adding costs, there are a truckload of options for allocating a cost. I can't seem to find any dumbed down tutorials on the internet either.

Does anyone have any advice, suggested links, tutorials etc that could be of use?

Thanks in advance.

Shane
Attached Files
File Type: zip Warburton.zip (235.5 KB, 15 views)
Reply With Quote
  #2  
Old 10-06-2014, 06:07 PM
JulieS JulieS is offline Microsoft Project  Managing Planned / Earned Value & Actual Costs Windows 7 64bit Microsoft Project  Managing Planned / Earned Value & Actual Costs Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Project can calculate Earned Value data as long as:

Costed resources (work resources with costs) assigned to tasks.
An accurate baseline saved
Status date set accurately
Tracking data applied to the project.

Project calculates earned value based upon percent complete.

Earned value data (BWCP, BCWS, ACWP, CPI, SPI etc) is available in tables (Earned Value, Earned Value Cost Indicators, Earned Value Schedule Indicators), in earned value visual reports.

I hope this helps.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Microsoft Project  Managing Planned / Earned Value & Actual Costs MS Project not calculating earned value correctly mtbtomo Project 1 10-23-2013 06:49 AM
Finding Earned Values for Different Baselines in a single project pratik6312 Project 1 08-22-2013 11:18 AM
Planned Versus Actual Completion abw1987 Project 8 12-04-2011 11:50 AM
Very simple / STUPID question about actual vs. planned hours sam-sam Project 0 12-07-2010 02:55 PM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:33 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft