JulieS JulieS is offline Microsoft Project  Managing Planned / Earned Value & Actual Costs Windows 7 64bit Microsoft Project  Managing Planned / Earned Value & Actual Costs Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Project can calculate Earned Value data as long as:

Costed resources (work resources with costs) assigned to tasks.
An accurate baseline saved
Status date set accurately
Tracking data applied to the project.

Project calculates earned value based upon percent complete.

Earned value data (BWCP, BCWS, ACWP, CPI, SPI etc) is available in tables (Earned Value, Earned Value Cost Indicators, Earned Value Schedule Indicators), in earned value visual reports.

I hope this helps.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Microsoft Project  Managing Planned / Earned Value & Actual Costs MS Project not calculating earned value correctly mtbtomo Project 1 10-23-2013 06:49 AM
Finding Earned Values for Different Baselines in a single project pratik6312 Project 1 08-22-2013 11:18 AM
Planned Versus Actual Completion abw1987 Project 8 12-04-2011 11:50 AM
Very simple / STUPID question about actual vs. planned hours sam-sam Project 0 12-07-2010 02:55 PM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:28 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft