Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 10-06-2014, 08:10 AM
basileus basileus is offline Work between Two Dates Windows 8 Work between Two Dates Office 2013
Novice
Work between Two Dates
 
Join Date: Oct 2014
Posts: 1
basileus is on a distinguished road
Default Work between Two Dates

Hi

First of all, I'm using the German MS Project 2013 version. So I don't know if the words I use about things in MS Project are exactly like I translate them.



My problem, I would like to specify an activity with a start and end date and needed work hours. Duration is not important for me, because the ressource/people can do this activity in this start/end frame when they want. And because it's a private project, work times (8h per day) are also not important, perhaps people do activities in the evening, perhaps during night.

For example I have activity "Project Structure Plan", which will take 10h to complete and can be done between 1.10.14 and 10.10.14.

How can I configure MS Project for this? I tried with automatic/manual activities, activity type "fix duration", "fix work", but nothing works like I want. Everytime MS Project is changing duration, start/end date or work time. Or changes work time if I add another ressource.

Thank you for your help.
Reply With Quote
  #2  
Old 10-06-2014, 06:10 PM
JulieS JulieS is offline Work between Two Dates Windows 7 64bit Work between Two Dates Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Set the task as fixed duration, non-effort driven, autoscheduled. You can then assign the resources (Task Form) and enter the amount of work. Project will calculate the units required to spread the work out over the duration.

I hope this helps.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Scheduling Chained Work Effort with Unchained Work Effort Starkweather Project 1 05-24-2014 12:37 PM
Work between Two Dates work of labor vs work of excavator ketanco Project 1 02-11-2014 08:53 AM
Work between Two Dates Changing Actual Finish dates changes original Finish dates SomewhereinTX Project 3 12-20-2013 10:25 AM
Missing some work from work really need help lukepierce222 Word 6 04-19-2012 08:41 AM
Work between Two Dates work vs regular work. and how regular work works user0044 Project 5 03-06-2012 07:28 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:32 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft