Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 09-30-2014, 12:43 PM
ketanco ketanco is offline % complete by duration Windows 7 64bit % complete by duration Office 2010 64bit
Expert
% complete by duration
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default % complete by duration

my project starts mid september and ends mid march. i want to see, what will be the overall % complete at the end of the year, as of december 31. how can i do that?

i dont have any resources assigned.. everything is entered in duration only and i update it by updating percent complete when i do updates.
Reply With Quote
  #2  
Old 09-30-2014, 01:12 PM
JulieS JulieS is offline % complete by duration Windows 7 64bit % complete by duration Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Use the Update Project command and set the status date of 31 December. Do NOT save changes.
Reply With Quote
  #3  
Old 09-30-2014, 01:57 PM
ketanco ketanco is offline % complete by duration Windows 7 64bit % complete by duration Office 2010 64bit
Expert
% complete by duration
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

thanks, it is good way... is there any other way to do this? just for learning, otherwise this works well

i checked the task usage view and couldnt see how else it can be done.

the only way i could think of was - (and i thought of it because a cumulative cost field exist in tas view), i entered durations in terms of cost , such as, if it is 7 day duration i entered $7 - just for the sake of seeing it , and not assigning any cost ofg course, i was just doing it by means of cost fields. i had no costs assigned in my project yet anyway.

then i pasted the date range and cumulative cost (duration) to excel... and made a graph. the results were almost the same.
Reply With Quote
  #4  
Old 09-30-2014, 02:22 PM
JulieS JulieS is offline % complete by duration Windows 7 64bit % complete by duration Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I don't follow your question "is there any other way to do this". Do what?

The Task Usage view shows you tasks and assignments. If you don't have resources, you don't have assignments.

If you want costs, you'll either need to:

Create resources with costs and assign them.
Use Cost resources
Use Fixed Costs

Project will not suddenly apply costs and there will be no data in the cumulative cost field.
Reply With Quote
  #5  
Old 10-01-2014, 06:39 AM
ketanco ketanco is offline % complete by duration Windows 7 64bit % complete by duration Office 2010 64bit
Expert
% complete by duration
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

Quote:
Originally Posted by JulieS View Post
I don't follow your question "is there any other way to do this". Do what?
to show percent complete in a way other than you told before... is there?

ok i was just trying to describe another way i did to do that, please ignore that part...
Reply With Quote
  #6  
Old 10-01-2014, 07:35 AM
JulieS JulieS is offline % complete by duration Windows 7 64bit % complete by duration Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Percent complete is a duration measurement. Percent work complete is a work measurement - as you don't have resources assigned this won't work. You can use Physical % complete but that requires:
1) pre-planning or the summary tasks will not update.
2) manual entry for each task. The update project command will not change physical % complete.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Duration days changing when updating % complete slinkster Project 14 07-17-2014 08:29 AM
% complete by duration physical complete %, regular work, vs % complete ketanco Project 1 06-16-2014 11:08 AM
Physical % Complete and Task Duration ChuckM Project 3 02-09-2014 09:21 AM
% complete by duration complete % and physical complete % ketanco Project 3 05-25-2012 08:19 AM
% complete by duration % Complete (Actual) vs % Complete (Should) Carlos Maximo Project 3 12-06-2011 12:01 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:07 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft