ketanco ketanco is offline adjusting calendar for a task and viewing calendar day result Windows 7 64bit adjusting calendar for a task and viewing calendar day result Office 2010 64bit
Expert
adjusting calendar for a task and viewing calendar day result
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default adjusting calendar for a task and viewing calendar day result

I have a task of 10 days, workdays. It has the normal calendar of 5 days a week and 8 hours a day. It is 0% complete right now. My tasks are effort driven and fixed units, so everything is as in default.
I also have a column for displaying calendar days. I had done that myself before with a formula and it is working fine.
So for my task of 10 days for example, that column shows 14 days
Here is my questions:
Question 1) When I change the calendar of that task, to a 24 hour calendar, the calendar day column shows 3 days.
When I change it to a 7 day calendar, the calendar day column shows 10 days.
But even if I choose fix duration or fixed work option and then make these changes, I still get the same outcome upon change. Should it not be different results?

Question 2) This one I did as experiment. I did not used “work” column in this schedule before so everything was zero. I inserted a work column, and for this task I assigned a random work amount of 100
But when I did the changes as stated above, the 100 never changed, for any option. Why?

Question 3) something is fixed for this task and when I change my calendars it is just dividing that fixed quantity to find the new calendar day duration. If it is fixed units, I don’t see a column for it. How can I see that fixed thing that the calculations are based upon? Also when I change to 24 hour calendar, would it not be 3.33 days? Why is it 3?
Reply With Quote
  #2  
Old 09-26-2014, 05:15 PM
JulieS JulieS is offline adjusting calendar for a task and viewing calendar day result Windows 7 64bit adjusting calendar for a task and viewing calendar day result Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Please share your formula. A 10 day duration task starting on a Monday and ending 10 working days later is really only 12 calendar days (assuming Saturday and Sunday are non-working) - so I don't know how you got 14 days.

What date/time does the task begin and end?

Regarding your second question:
Question 2) This one I did as experiment. I did not used “work” column in this schedule before so everything was zero. I inserted a work column, and for this task I assigned a random work amount of 100
But when I did the changes as stated above, the 100 never changed, for any option. Why?


Work is not related to duration unless you have resources assigned to the task. It is the assignment units (Peak) that creates the relationship between work and duration. Assuming the task is fixed units and you have resource(s) assigned - if you increase duration, work will increase. But without assignments, there is no relationship between work and duration.

Regarding:
Question 3) something is fixed for this task and when I change my calendars it is just dividing that fixed quantity to find the new calendar day duration. If it is fixed units, I don’t see a column for it. How can I see that fixed thing that the calculations are based upon? Also when I change to 24 hour calendar, would it not be 3.33 days? Why is it 3?

i don't understand "something is fixed for this task". Are you referring to task type (Fixed Duration, Fixed Units, Fixed Work)? These have no impact unless you have resource assigned. The definition of a day is 8 hours - if you change to a 24 hours calendar the "day" definition doesn't change. Depending upon when the task begins and ends, you may see 3.33 days or 3 days.
Please post your formula.
Reply With Quote
  #3  
Old 09-30-2014, 12:41 PM
ketanco ketanco is offline adjusting calendar for a task and viewing calendar day result Windows 7 64bit adjusting calendar for a task and viewing calendar day result Office 2010 64bit
Expert
adjusting calendar for a task and viewing calendar day result
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

here is my formula

ProjDateDiff(Scheduled Start,Scheduled Finish,"7 Day calendar")


for question 3, by saying somethig is fixed i meant i didnt understand how does it do the dividing. it divindes some fixed quantity to new day size. or where is my thinking wrong
Reply With Quote
  #4  
Old 09-30-2014, 01:10 PM
JulieS JulieS is offline adjusting calendar for a task and viewing calendar day result Windows 7 64bit adjusting calendar for a task and viewing calendar day result Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

With a task starting today (Tuesday 30 Sept at 08:00) with 10 days duration using the Standard calendar - the task ends 13 October at 5:00 pm.

Assuming you have made the "7 Days Calendar" also as 08:00 to 17:00 and using your formula - I see 14 days in the custom field.

When I apply the 24 hours calendar, the duration in the standard duration field still reads 10 days. The task begins 30 Sept at 08:00 and ends Oct 3 at 16:00. The duration in the calculated field is 3.88 days.

Regarding task type - as I said it does NOT play into task duration unless you have resources assigned. If you have resources assigned then the "fixed" value is not altered by Project when you alter one of the other values. For example:

Fixed Units task type:
you change Work, Project recalculates Duration
you change Duration, Project recalculates Work

Fixed Duration task type:
you change Work, Project recalculates units
you change Units, Project recalculates Work

But again - this only applies if you have resources assigned. If you have resources assigned and you are using Task Calendars, unless you check the box "scheduling ignores resource calendars" the task will be scheduled during common working time between the task calendar and the resource calendar.

If possible, I suggest getting some hands-on training in Project. It is by no means an intuitive tool. I can only help so much by answering questions you have been posting. A good 2 to 3 days course will help clear up many questions.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Outlook 2013 calendar reminders disabled on my calendar but show on boss's when i send invites WUPJ Outlook 0 08-06-2014 05:29 AM
Calendar events, directly associated to Task(s) Jeff@EXITassurance.com Outlook 0 03-16-2014 08:42 AM
showing calendar days by keeping normal workday calendar ketanco Project 11 11-01-2013 08:27 AM
adjusting calendar for a task and viewing calendar day result Is it possible to show the Task due date in the calendar? Lin Outlook 1 07-26-2010 05:34 AM
Outlook 2003 Viewing INbox and Calendar in the same View kingtut19 Outlook 0 03-23-2006 10:09 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:55 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft