billcary billcary is offline MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table Windows 7 64bit MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table Office 2013
Novice
MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table
 
Join Date: Sep 2014
Posts: 2
billcary is on a distinguished road
Default MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table

Hello -

I am creating a report in MS Project 2013. When I create a time-phased line chart containing ACWP, the ACWP shown in the chart for the current status date does not match the ACWP shown in a table (same status date) or in a column chart within the same report. The table and the column chart show $10,401.45, while the line chart shows $90,401.45. Images provided below for reference. Also for reference - the ACWP shown in the report's tabular view exactly matches the ACWP shown in the Earned Value table in Project's Gantt chart view.

ACWP for 9/8/2014





(Matches values shown in Gantt view and in a column chart in the report.)







The difference between the two ACWP values is exactly $80,000. This precisely matches the value of a specific task in the schedule that is set up as a milestone and has no associated hours, but DOES have a cost resource assigned with an $80,000 cost. I am not certain why the chart is picking up this additional $80,000 when the tables do not show it. (Also note that when I export the data to Excel using "Visual Reports," the $80,000 task is not included in the exported ACWP.

Any idea why I am seeing this seeming inconsistency?

Thanks!
Reply With Quote
  #2  
Old 09-18-2014, 02:29 PM
JulieS JulieS is offline MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table Windows 7 64bit MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi Bill,
I've answered you at stack exchange.

http://pm.stackexchange.com/question...tch-acwp-in-co
Reply With Quote
  #3  
Old 09-19-2014, 11:11 AM
billcary billcary is offline MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table Windows 7 64bit MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table Office 2013
Novice
MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table
 
Join Date: Sep 2014
Posts: 2
billcary is on a distinguished road
Default

Thanks Julie. I replied with comments in the same thread on Stack Exchange. For quick reference for other readers, my response is below:
--------------------------------------------------------------------------------------
Thanks Julie - I appreciate it. I tried a couple of different things based on your post. First, I removed the fixed cost entry for the task in question, and instead created a cost resource (with a per unit rate of $80,000). I assigned the cost resource to the task with an estimated usage of 1 unit, then re-baselined that task (with roll-up to summary tasks.) When I did this, for some reason, the Planned Value (BCWS) would not pick up the $80,000 cost, even when I set the status date well beyond the time for which I entered the actual usage. Neither did the Earned Value (BCWP). However, the ACWP did pick up the $80,000 cost. So it still left me with very large artificial variances. In the end, I simply decided to remove that element from the schedule entirely, since it has no potential to deviate from the planned value, and I am more concerned, at this time, with tracking the progress of the actual work effort.

In addition, upon further reflection, I decided that the magnitude of the $80,000 cost was so large in proportion to the relatively small weekly labor costs of $3K-$4K that a positive schedule variance for that task (if completed ahead of schedule) would severely obscure any negative variances in the labor tasks when the project was viewed as a whole. (At least until the original planned date of the $80,000 task had passed.) This was an additional reason I chose to drop it.

This results in an overall cost picture that is not entirely accurate since it doesn't include the $80,000, but it allows me to more effectively track the work being done on the project. And in case anyone is wondering, this technique is being used on a small project as a "work out the kinks" exercise before being applied to larger efforts. That is why I am spending so much monitoring effort on a set of tasks that is relatively small.
Reply With Quote
  #4  
Old 09-22-2014, 07:10 AM
JulieS JulieS is offline MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table Windows 7 64bit MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi Bill.

Replied at Stack Exchange.
Reply With Quote
Reply

Tags
acwp

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Cash flow reports in MS Project 2013 sansrini18 Project 3 09-09-2013 06:06 AM
column chart prob sturner333 Excel 0 01-09-2013 12:29 PM
Column Chart Average blaqsheep Excel 0 02-07-2012 07:04 PM
MS Project Resource Chart fherbert PowerPoint 0 09-09-2010 12:20 PM
Bar chart in Project 2010. aligahk06 Project 0 07-04-2010 07:37 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:50 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft