Old 09-17-2014, 05:21 PM
JulieS JulieS is offline Milestones with different start and finish dates Windows 7 64bit Milestones with different start and finish dates Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

There is a checkbox in Task information that allows you to mark a non-zero day duration task as a milestone. Is that what you mean by "a milestone (activity with zero duration) with different start and finish dates"

I'm afraid I don't understand what you are asking. How many tasks are we talking about - I see BB, AA, B. Can you please try again? Project will pay attention to link relationships and attempt to move successor task progress where it's logical. Please attach a file or a picture of what you're talking about.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Milestones Filter to show Milestones within 2 months pmgreen Project 7 08-14-2014 09:39 AM
Milestones with different start and finish dates Changing Actual Finish dates changes original Finish dates SomewhereinTX Project 3 12-20-2013 10:25 AM
start and finish dates exceeding duration joday48 Project 0 06-27-2012 04:55 AM
Milestones with different start and finish dates duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM
Milestones with different start and finish dates displaying start and finish times as absolute numbers instead of dates benson.wallace Project 2 12-05-2010 07:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:24 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft