2 Shift - Project Calendar
 
Join Date: Mar 2014
Posts: 7
Mav is on a distinguished road
Default 2 Shift - Project Calendar

I'm struggling to create a 2 shift (2nd shift) calendar in MS Project that calculates correctly.



I want to be able to enter a "2 Shift" calendar for my resource and have a 16 hr work day (two 8 hour shifts). When I enter 8 hours it should calculate .5 days duration. When I switch the calendar back to standard it should be 1 day for 8 hours work.

Could someone help with this? Maybe post a MS Project 2010 file with the calendar created so I can see it?

Much appreciated
Reply With Quote
  #2  
Old 09-08-2014, 10:42 AM
JulieS JulieS is offline 2 Shift - Project Calendar Windows 7 64bit 2 Shift - Project Calendar Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

See if the attached file helps. I have a project calendar with working times from 7:00 am to 12:00 am with breaks during when the resources should be not working. My definition of "day" in File > Options, Schedule is 16 hours, week is 80 hours, default start and finish align with Project calendar.

I have a first shift calendar from 07:00 to 3:30 with a half-hour lunch. I have a second shift calendar from 3:30 pm to 12:00 am with a half-hour lunch. I have two resources each one assigned to one of the calendars.
Attached Files
File Type: zip shifts.zip (26.7 KB, 22 views)
Reply With Quote
Reply

Tags
calendar issue, calendars, project calendar

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
2 Shift - Project Calendar Noob here - I need a shift calendar by days with count of shift. freeman Excel 8 09-12-2012 08:45 AM
2 Shift - Project Calendar Shift key erratic Razz Outlook 2 05-04-2011 05:35 PM
How can I use persian (solar) calendar in ms project 2010? mammadkoma Project 0 11-13-2010 06:01 AM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:09 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft