#1
|
|||
|
|||
Gantt calendar view
Hi All
I have set up a programme that has a start date of 01/09/14; yet in the gantt view it says 01/09/15. I have gone into the project bar on the ribbon and it say the correct start date yet on the gantt it reads a year later. Its as if project thinks the project starts in 2015 when it doesnt. Can anyone help me please? Last edited by deanop2; 09-03-2014 at 11:03 AM. |
#2
|
|||
|
|||
Check your fiscal year settings. File > Options, Schedule. Likely your fiscal year is set for something other than January. If you need fiscal years other than January, click the check box "Use starting year for FY numbering."
|
#3
|
|||
|
|||
Thankyou very much JulieS, that was the problem.
Solved Cheers |
#4
|
|||
|
|||
Great. Glad it helped and thanks for the feedback.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Calendar view - export to .pdf | EC37 | Project | 3 | 06-18-2014 12:53 PM |
checking tasks complete from main gantt view | sundance1 | Project | 1 | 01-29-2013 10:31 AM |
Gantt Chart with split view | Intruder | Project | 5 | 12-20-2012 08:35 AM |
Split Gantt view like an Excel spreadsheet | NMuser | Project | 3 | 08-21-2012 04:30 AM |
Calendar default view | ReviTULize | Outlook | 0 | 02-29-2012 03:22 PM |