![]() |
#1
|
|||
|
|||
![]()
Hola,
question: Is there a way in MS Project 2010 to have a field display the values/names of the resource sheet independently of the task? More detailed: I have a custom field "Contacts1" and "contacts2" which I would like to have the resource names as valid values. I want them to be independent of the actual "Resource Names" field and the task. I want to be able to select e.g. 3 names for "Contacts1" and another 4 for "Contacts2". So far I wasn't able to figure it out. Is there a formular I can use on the custom fields? I tried using "Resource Names" as field name and renaming to Contacts1 and Contacts2, however, in that case they're interlinked and when changing the values for one field, it changes the values for all fields with resource names ![]() Thanks in advance ![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
joday48 | Project | 6 | 08-19-2014 05:49 AM |
![]() |
Jvallee | Mail Merge | 9 | 04-16-2014 06:30 PM |
![]() |
scott.hannaford | Project | 1 | 10-21-2013 05:32 AM |
How to enter names in Resource Pool/names | pstein | Project | 1 | 03-26-2012 07:37 AM |
Export resource custom field to excel chart | jtorres | Project | 0 | 03-15-2011 05:16 AM |