Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 08-19-2014, 07:44 PM
meileetan meileetan is offline Fixed end but variable start (and duration) Windows Vista Fixed end but variable start (and duration) Office 2007
Novice
Fixed end but variable start (and duration)
 
Join Date: Aug 2012
Posts: 16
meileetan is on a distinguished road
Default Fixed end but variable start (and duration)

I have an activity that must end by a certain date. Start date depends on the completion of a few tasks and it can start as soon as one of these dependent tasks end. To illustrate:
Dependent task 1 ends Jan 1
Dependent task 2 ends Feb 1
Variable task must end by April 30. It can start as early as Jan 1 (i.e. when Dependent Task 1 ends) but if Dependent task 1 gets delayed to March 1, then this Variable task can start on Feb 1 (i.e. when Dependent Task 2 ends).



To further complicate matters, the duration of Variable task must be at least 5 days, i.e. cannot start later than April 30-5d.

How can I best reflect this in MS Project?
Reply With Quote
  #2  
Old 08-20-2014, 06:46 AM
JulieS JulieS is offline Fixed end but variable start (and duration) Windows 7 64bit Fixed end but variable start (and duration) Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm afraid there isn't a direct way to accomplish all of the needs.
You can set a deadline on the Variable task.
You can set a Start No Later Than constraint on the variable task.

You can make the variable task a successor of the Jan tasks however a F to S relationship is always the later of the two. So if the first task moves to past Feb 1, you'll need to manually remove the link to the Jan task and re-link to the Feb 1 task.
Reply With Quote
  #3  
Old 08-20-2014, 06:31 PM
meileetan meileetan is offline Fixed end but variable start (and duration) Windows Vista Fixed end but variable start (and duration) Office 2007
Novice
Fixed end but variable start (and duration)
 
Join Date: Aug 2012
Posts: 16
meileetan is on a distinguished road
Default

Thanks Julie. How do I set a "start no later than" constraint on the variable task? I've already set a "end no later than" constraint = 30 April. Or were you saying I can do only one of the 2, not both?
Reply With Quote
  #4  
Old 08-22-2014, 06:54 AM
JulieS JulieS is offline Fixed end but variable start (and duration) Windows 7 64bit Fixed end but variable start (and duration) Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You cannot set two constraints on a single task. Use a deadline for the finish date and the SNET constraint.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Fixed end but variable start (and duration) How to add A fixed cost per day for the duration of the project? vdLRSA Project 3 08-11-2014 02:26 PM
Fixed end but variable start (and duration) Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all Evgeny Project 3 01-03-2013 06:45 AM
start and finish dates exceeding duration joday48 Project 0 06-27-2012 04:55 AM
Fixed end but variable start (and duration) How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM
Task duration between 2 fixed milestones cettolox Project 3 01-24-2012 06:33 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:29 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft