joday48 joday48 is offline Resource assignment with resource calendars Windows 7 64bit Resource assignment with resource calendars Office 2010 32bit
Novice
Resource assignment with resource calendars
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default Resource assignment with resource calendars

Hi all




Normally when I set a schedule up with every resource using the same times in their calendars, and I then decide that resource (A) will spend 70% of their time on a 2 day task, and resource (B) will spend 30% of their time on the same task, it does exactly what I would expect and schedules resource (A) to work 0.7 day and resource (B) 0.3 day.

However, how do I get it to schedule resource (A) to spend their total available time on the task each day? So = 1 day on the first day and 0.4 on the second?, and resource (B) to spend their total available time (0.6) on the first day, rather than splitting it out so that resource (A) does 0.7 day for 2 days and resource (B) does 0.3 days for 2 days?


Thank you

Jo
Reply With Quote
  #2  
Old 08-18-2014, 02:54 PM
JulieS JulieS is offline Resource assignment with resource calendars Windows 7 64bit Resource assignment with resource calendars Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm not sure I understand your question. If you assign a resource at 70% assignment units Project calculates work based upon Task Duration * Units. Assuming an 8 hour day - the resource's work is 11.2 hours.

If you want the resource to work the 11.2 hours in shorter time, assign the resource at 100% and specify the 11.2 hours of work. Project will recalculate the duration to 1.4 days.

Split your screen to show the Task Form in the lower pane and enter the work for each resource as you make the assignment.
Reply With Quote
  #3  
Old 08-19-2014, 02:00 AM
joday48 joday48 is offline Resource assignment with resource calendars Windows 7 64bit Resource assignment with resource calendars Office 2010 32bit
Novice
Resource assignment with resource calendars
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default

Hi Julie

I think I am confusing myself!

Basically I have multiple resources assigned to the same tasks throughout my schedule. I have levelled the schedule and here lies the issue. There are often instances where a resource will not have any work loaded for them for a long period, because they are waiting for another/other resources to become available before they can move on to the next task.

There are also lots of days where they are working but not being fully utilised too.

Is this simply because we have too many resources assigned to the same tasks and there is no way around the issues we are finding?

Can you offer a solution that doesn't involve creating the same task 4 times (if 4 people are working on it at the same time) and assigning them all individually to the duplicated tasks? the schedule will be so long if I have to do this.

Any help you can offer would be much appreciated

Thanks

Jo
Reply With Quote
  #4  
Old 08-19-2014, 05:13 AM
JulieS JulieS is offline Resource assignment with resource calendars Windows 7 64bit Resource assignment with resource calendars Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The resource leveling command is used to resolve resource overallocations. It is not a resource optimization tool. If the resources are not fully utilized, assign them at their maximum units - then at least if the schedule is leveled they will be fully assigned when they are assigned.
You may also want to allow the leveling command to level individual assignments - that way if one resource is not overallocated s/he can work on the task independent of other works.
Regarding gaps - there really isn't any way around that. If Resource A is waiting on an output from a task that Resource B is working on - there may be times when A is just waiting without other tasks.
Reply With Quote
  #5  
Old 08-19-2014, 05:19 AM
JulieS JulieS is offline Resource assignment with resource calendars Windows 7 64bit Resource assignment with resource calendars Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I see you've also posted to:

http://answers.microsoft.com/en-us/o...5-0d6f111cd299

Please do not post the same question to multiple places. I'll assume you'll get the answers you need at the other forum.
Reply With Quote
  #6  
Old 08-19-2014, 05:42 AM
joday48 joday48 is offline Resource assignment with resource calendars Windows 7 64bit Resource assignment with resource calendars Office 2010 32bit
Novice
Resource assignment with resource calendars
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default

Julie

Apologies

I was unaware the same people worked across all forums. I was just posting in different places as I was hoping to get an answer soonest.

Thank you for explaining the answer to my question.

Jo
Reply With Quote
  #7  
Old 08-19-2014, 05:49 AM
JulieS JulieS is offline Resource assignment with resource calendars Windows 7 64bit Resource assignment with resource calendars Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

No trouble, Jo. The people responding to the questions are volunteers, so we ask that you post the question to one forum and be patient.

You're welcome for the assist.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource Assignment Summary Line Not Adding Up Correctly PeteS Project 2 07-18-2014 06:24 AM
Resource assignment with resource calendars Over-allocated resource - resource holiday scott.hannaford Project 1 10-21-2013 05:32 AM
resource issue safaa Project 1 11-20-2012 05:41 AM
Resource Calendars caz46 Project 0 02-12-2011 05:31 AM
Resource use on tasks Proj03 Project 0 01-24-2011 01:40 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:59 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft