Hi all




Normally when I set a schedule up with every resource using the same times in their calendars, and I then decide that resource (A) will spend 70% of their time on a 2 day task, and resource (B) will spend 30% of their time on the same task, it does exactly what I would expect and schedules resource (A) to work 0.7 day and resource (B) 0.3 day.

However, how do I get it to schedule resource (A) to spend their total available time on the task each day? So = 1 day on the first day and 0.4 on the second?, and resource (B) to spend their total available time (0.6) on the first day, rather than splitting it out so that resource (A) does 0.7 day for 2 days and resource (B) does 0.3 days for 2 days?


Thank you

Jo
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource Assignment Summary Line Not Adding Up Correctly PeteS Project 2 07-18-2014 06:24 AM
Resource assignment with resource calendars Over-allocated resource - resource holiday scott.hannaford Project 1 10-21-2013 05:32 AM
resource issue safaa Project 1 11-20-2012 05:41 AM
Resource Calendars caz46 Project 0 02-12-2011 05:31 AM
Resource use on tasks Proj03 Project 0 01-24-2011 01:40 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:07 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft